[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142235":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1142235,799,1,"单选题","某项目招标时，因图纸、规范准备不充分，不能据此确定合同价格，而仅能制定一个估算指标，则适宜采用的合同形式（）。2018真题",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","成本加固定费用合同",false,{"key":16,"text":17,"correct":14},"B","最大成本加费用合同",{"key":19,"text":20,"correct":14},"C","成本加固定比例费用合同",{"key":22,"text":23,"correct":24},"D","成本加奖金合同",true,"本题考查的是成本加酬金合同的形式。在招标时，当图纸、规范等准备不充分，不能据以确定合同价格，而仅能制定一个估算指标时可采用成本加奖金合同。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]