[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142232":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142232,799,1,"单选题","在非代理型施工管理模式（CM模式）的合同中，通常采用（ ）合同。2014",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","成本加固定费用",false,{"key":16,"text":17,"correct":14},"B","成本加固定比例费用",{"key":19,"text":20,"correct":21},"C","最大成本加费用",true,{"key":23,"text":24,"correct":14},"D","成本加奖金","本题考查的是成本加酬金合同的形式。在非代理型（风险型）CM模式的合同中应采用最大成本加费用的合同形式。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]