[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142220":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142220,799,1,"单选题","工程咨询服务合同的计价方式主要采用（）。2018真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总价合同和成本加酬金合同",true,{"key":16,"text":17,"correct":18},"B","总价合同和单价合同",false,{"key":20,"text":21,"correct":18},"C","单价合同和成本加酬金合同",{"key":23,"text":24,"correct":18},"D","总价合同、单价合同和成本加酬金合同","本题考查的是工程咨询合同计价方式。工程咨询服务合同的计价主要采用总价和成本加酬金方式。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]