[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142215":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142215,799,1,"单选题","有关于建设工程项目总承包单位工作内容，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","负责办理项目的审查、核准或手续，取得项目用地的使用权",false,{"key":16,"text":17,"correct":18},"B","按照合同约定：完成设计、采购、施工、竣工试验和竣工后试验",true,{"key":20,"text":21,"correct":14},"C","完成拆迁补偿工作，使项目具备法律规定的开工条件",{"key":23,"text":24,"correct":14},"D","项目总承包单位可自主确定设计人员和设计分包者","项目总承包单位应按照合同约定，完成设计、采购、施工、竣工试验和竣工后试验。如果设计工作需要分包的，应经业主代表同意。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]