[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142207":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142207,799,2,"多选题","根据《建设工程质量管理条例》，转包行为有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发包人与施工总承包商签订合同后又向总承包商指定分包",false,{"key":16,"text":17,"correct":18},"B","承包商将其承包的全部建设工程转给他人承包",true,{"key":20,"text":21,"correct":18},"C","承包商将其承包的全部工程肢解后以分包的名义分别转给他人承包",{"key":23,"text":24,"correct":14},"D","施工总承包商将其承包的主体结构工程施工任务全部转包给他人承包",{"key":26,"text":27,"correct":14},"E","分包人将其承包的建设工程再分包","BC","本题主要考查禁止转包或再分包。 BC项： 根据《建设工程质量管理条例》规定，承包人不得将其承包的全部工程转包给第三人，或将其承包的全部工程肢解后以分包的名义转包给第三人。以上行为可视为转包。所以BC项正确。 A项：不属于转包行为，但是相关法规禁止。所以A项错误。 D项：施工总承包商将其承包的主体结构工程施工任务全部转包给他人承包属于非法分包行为。所以D项错误。 E项：分包人将其承包的建设工程再分包属于再分包行为。所以E项错误。 综上所述，本题正确答案为BC。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]