[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142200":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142200,799,1,"单选题","根据《建设工程施工劳务分包合同（示范文本）》，工程承包人应在确认劳务分包人递交的结算资料后（ ）天内向劳务分包人支付劳务报酬尾款。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","28",{"key":23,"text":24,"correct":14},"D","30","本题考核的是劳务报酬最终支付的内容。 劳务报酬最终支付： （1）全部工作完成，经承包人认可后14天内，劳务分包人向承包人递交完整的结算资料，双方按照本合同约定的计价方式，进行劳务报酬的最终支付； （2）承包人收到劳务分包人递交的结算资料后14天内进行核实，给予确认或者提出修改意见。承包人确认结算资料后14天内向劳务分包人支付劳务报酬尾款； （3）劳务分包人和承包人对劳务报酬结算价款发生争议时，按合同约定处理。 根据第（2）项得出本题答案。 综上所述，正确选项为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]