[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142197":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142197,799,1,"单选题","（2019年真题）关于专业工程分包人责任和义务的说法,正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分包人必须服从发包人直接发出的指令",false,{"key":16,"text":17,"correct":14},"B","必须完成规定的设计内容,并承担由此发生的费用",{"key":19,"text":20,"correct":21},"C","分包人应履行总包合同中与分包工程有关的承包人的义务,另有约定除外",true,{"key":23,"text":24,"correct":14},"D","在合同约定的时间内,向监理人提交施工组织设计,并在批准后执行","P276-278 A说法不严谨，分包人须服从承包人转发的发包人或工程师与分包工程有关的指令; B错误，按照合同约定的时间,完成规定的设计内容,承包人承担由此发生的费用; D错误，在合同约定的时间内，向承包人提交详细的施工组织设计,承包人应在专用条款约定的时间内批准，分包人方可执行。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]