[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142196":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142196,799,1,"单选题","（2019年真题）根据《建设工程施工专业分包合同(示范文本)》,关于发包人、承包人和分包人关系的说法,正确的是( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人向分包人提供具备施工条件的施工场地",false,{"key":16,"text":17,"correct":18},"B","就分包范围内的有关工作,承包人随时可以向分包人发出指令",true,{"key":20,"text":21,"correct":14},"C","分包人可直接致函发包人或工程师",{"key":23,"text":24,"correct":14},"D","分包合同价款与总承包合同相应部分价款存在连带关系","P276-278 分包人须服从承包人转发的发包人或工程师与分包工程有关的指令。未经承包人允许，分包人不得以任何理由与发包人或工程师发生直接工作联系，分包人不得直接致函发包人或工程师，也不得直接接受发包人或工程师的指令。如分包人与发包人或工程师发生直接工作联系，将被视为违约，并承担违约责任。 分包合同价款与总包含同相应部分价款无任何连带关系。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]