[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142191":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1142191,799,1,"单选题","关于分包合同价款的表述，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分包工程合同价款应与总承包合同相应部分价款一致",false,{"key":16,"text":17,"correct":14},"B","分包工程合同价款应低于总承包合同相应部分价款",{"key":19,"text":20,"correct":14},"C","分包工程合同价款应高于总承包合同相应部分价款",{"key":22,"text":23,"correct":24},"D","分包合同价款与总包合同相应部分价款无任何连带关系",true,"本题主要考查分包合同价款。 建设工程分包合同价款与总包合同相应部分价款无任何连带关系。建设工程施工合同根据合同计价方式的不同，一般情况下分为三大类型，即总价合同、单价合同和成本加酬金合同。 综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]