[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142169":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142169,799,1,"单选题","（2020年真题）根据《建设工程施工合同(示范文本)》，工程隐蔽部位经承包人自检确认具备覆盖条件的，承包人应在共同检查前（ ）小时书面形式通知监理人检查。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","48",true,{"key":16,"text":17,"correct":18},"B","12",false,{"key":20,"text":21,"correct":18},"C","24",{"key":23,"text":24,"correct":18},"D","36","P265-276 除专用合同条款另有约定外，工程隐蔽部位经承包人自检确认具备覆盖条件的，承包人应在共同检查前48小时书面通知监理人检查，通知中应载明隐蔽检查的内容、时间和地点，并应附有自检记录和必要的检查资料。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]