[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142164":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142164,799,2,"多选题","根据《建筑工程施工合同（示范文本）》通用条款，除专用条款另有约定外，发包人的责任与义务有（）。2018真题",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","按照承包人实际需要的数量免费提供图纸",false,{"key":16,"text":17,"correct":18},"B","对施工现场发掘的文物古迹采取妥善保护措施",true,{"key":20,"text":21,"correct":18},"C","负责完善无法满足施工需求的场外交通设施",{"key":23,"text":24,"correct":18},"D","最迟于开工日期7天前向承包人移交施工现场",{"key":26,"text":27,"correct":14},"E","无条件向承包人提供银行保函形式的支付担保","BCD","本题考查的是施工承包合同文件。选项A，发包人应按照专用合同条款约定的期限、数量和内容向承包人免费提供图纸；选项E，除专用合同条款另有约定外，发包人要求承包人提供履约担保的，发包人应向承包人提供支付担保。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]