[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142162":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142162,799,1,"单选题","根据《建设工程施工合同（示范文本）》（GF-2013-0201），工程未经竣工验收，发包人擅自使用的，以（ ）为实际竣工日期。( 2015真题 )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人提交竣工验收申请报告之日",false,{"key":16,"text":17,"correct":18},"B","转移占有工程之日",true,{"key":20,"text":21,"correct":14},"C","监理人组织竣工初验之日",{"key":23,"text":24,"correct":14},"D","发包人签发工程接收证书之日","本题考查的是施工承包合同文件。工程未经竣工验收，发包人擅自使用的，以转移占有工程之日为实际竣工日期。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]