[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142160":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142160,799,1,"单选题","根据《建设工程施工合同（示范文本）》（GF—2013—0201），工作缺陷责任期自（ ）起计算。2014",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","合同签订日期",false,{"key":16,"text":17,"correct":14},"B","竣工验收合格之日",{"key":19,"text":20,"correct":21},"C","实际竣工日期",true,{"key":23,"text":24,"correct":14},"D","颁发工程接收证书之日","本题考查的是缺陷责任期的起始时间。缺陷责任期自实际竣工日期起计算，合同当事人应在专用合同条款约定缺陷责任期的具体期限，但该期限最长不超过24个月。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]