[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142145":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142145,799,1,"单选题","某独立土方工程按（工程量清单计价规范）计价。招标文件中预计工程量10万立方米，合同中规定：土方工程单价30元\u002F立方米。当实际工程量超过估计工程量10%时，超出部分价格调整为25元\u002F立方米。工程完成后实际工程量12万立方米，则该土方工程的结算工程款为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","355",true,{"key":16,"text":17,"correct":18},"B","350",false,{"key":20,"text":21,"correct":18},"C","325",{"key":23,"text":24,"correct":18},"D","300","本题考核的是建筑安装工程费用的动态结算。 因为（12-10）万m3\u002F10万m3=20%>10%，所以要对工程单价做调整，不需调整单价的工程量=10×（1+10%）万m3=11万m3，应调整单价的工程量=（12-11）万m3=1万m3，则该土方工程的结算工程款=11万m3×30元\u002Fm3+1万m3×25元\u002Fm3=355万元。 综上所述，正确选项为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]