[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142136":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142136,799,1,"单选题","由发包人供应的材料设备，承包人派人参加清点后由承包人妥善保管，（ ）支付相应保管费用。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人",false,{"key":16,"text":17,"correct":14},"B","供应商",{"key":19,"text":20,"correct":21},"C","发包人",true,{"key":23,"text":24,"correct":14},"D","监理人","本题主要考查建设工程施工合同的内容。 根据《建设工程施工合同（示范文本）》（GF--1999--0201）的规定，发包人供应的材料设备，承包人派人参加清点后由承包人妥善保管，发包人支付相应保管费用。因承包人原因发生丢失损坏由承包人负责赔偿。 综上所述，本题正确选项为C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]