[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142134":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142134,799,1,"单选题","根据《建设工程施工合同（示范文本）》，发包人未按合同约定预付工程款时，承包商可按合同约定向发包人发出要求预付的通知，发包人收到通知后仍不能按要求预付的，承包商最早可在发出通知后（ ）天停止施工。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",true,{"key":16,"text":17,"correct":18},"B","14",false,{"key":20,"text":21,"correct":18},"C","21",{"key":23,"text":24,"correct":18},"D","28","本题考核的是分包管理的内容。 《建设工程施工合同（示范文本）》规定：若发包人未按合同的约定预付工程款，承包人应在预付时间到期后7天内向发包人发出要求预付的通知。发包人收到通知后仍不按要求预付的。承包人可在发出通知7天后停止施工。发包人应从约定应付之日起按同期银行贷款率计算向承包人支付应付预付款的利息，并承担违约责任。 综上所述，本题正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]