[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142130":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142130,799,1,"单选题","发包人供应的材料设备使用前，由（ ）负责检验或试验。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":18},"B","承包人",true,{"key":20,"text":21,"correct":14},"C","工程师",{"key":23,"text":24,"correct":14},"D","政府有关机构","本题主要考查建设工程施工合同的内容。 根据《建设工程施工合同（示范文本）》（GF-99-0201），发包人供应的材料设备使用前，由承包人负责检验或试验，不合格的不得使用，检验或试验费用由发包人承担。 综上所述，本题正确选项为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]