[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142124":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142124,799,1,"单选题","工程师的检查检验不应影响施工的正常进行。如影响施工正常进行，检查检验不合格时，影响正常施工的费用由承包人承担。除此之外，影响正常施工的追加合同价款由（ ）承担，相应顺延工期。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人",false,{"key":16,"text":17,"correct":18},"B","发包人",true,{"key":20,"text":21,"correct":14},"C","设计单位",{"key":23,"text":24,"correct":14},"D","监理单位","本题主要考查影响施工的责任。 因发包人原因造成停工的，由发包人承担所发生的追加合同价款，赔偿承包人由此造成的损失，相应顺延工期；因承包人原因造成停工的，由承包人承担发生的费用，工期不予顺延。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]