[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142086":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142086,799,1,"单选题","根据我国《招标投标法》，若招标人需要对已发出的招标文件进行必要的澄清或者修改，应当至少在招标文件中规定的投标文件截止时间前的（ ）日，以书面形式通知所有招标文件收受人。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","14",false,{"key":16,"text":17,"correct":18},"B","15",true,{"key":20,"text":21,"correct":14},"C","28",{"key":23,"text":24,"correct":14},"D","30","本题考核的是招标文件进行必要的澄清或修改的时间。 《招标投标法》第二十三条规定：招标人对已发出的招标文件进行必要的澄清或者修改的，应当在招标文件要求提交投标文件截止时间至少十五日前，以书面形式通知所有招标文件收受人。该澄清或者修改的内容为招标文件的组成部分。 综上所述，正确选项为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]