[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142084":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142084,799,1,"单选题","根据《招标投标法》，招标人对已发出的招标文件进行必要的澄清或修改的，应当在招标文件要求提交投标文件截止时间至少（ ）日之前书面通知。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","15",true,{"key":20,"text":21,"correct":14},"C","14",{"key":23,"text":24,"correct":14},"D","21","本题主要考查招标信息的修正。 招标人对已发出的招标文件进行必要澄清或修改的，应当在招标文件要求提交投标文件截止时间至少15日前书面通知。 综上所述，正确选项为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]