[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142066":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142066,799,1,"单选题","招标人和中标人在签订合同的谈判中，为了防范货币贬值或者通货膨胀的风险一般通过（ ）约定风险承担方式。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","调整投标价格",false,{"key":16,"text":17,"correct":18},"B","价格调整条款",true,{"key":20,"text":21,"correct":14},"C","调整中标价格",{"key":23,"text":24,"correct":14},"D","调整工作范围","本题考核的是建设工程施工承包合同谈判的价格调整条款。 对于工期较长的建设工程，容易遭受货币贬值或通货膨胀等因素的影响，给承包人造成较大损失。价格调整条款可以比较公正地解决这一承包人无法控制的风险损失。无论是单价合同还是总价合同，都可以确定价格调整条款，即是否调整以及如何调整等。 合同计价方式以及价格调整方式共同确定了工程承包合同的实际价格，直接影响承包人的经济利益。 综上所述，正确选项为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]