[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141968":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141968,799,1,"单选题","建设工程生成安全事故应急预案中，针对深基坑开挖可能发生的事故，相关危险源和应急保障而制定的计划属于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","综合应急预案",false,{"key":16,"text":17,"correct":14},"B","现场处置方案",{"key":19,"text":20,"correct":21},"C","专项应急预案",true,{"key":23,"text":24,"correct":14},"D","现场应急预案","本题主要考查生产安全事故应急预案。 生产安全事故应急预案体系的构成包括综合应急预案、现场处置方案、专项应急预案。 针对深基坑开挖可能发生的事故属于专项应急预案。 综上所述，本题正确选项为C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]