[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141949":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141949,799,2,"多选题","关于安全技术交底内容及要求的说法，正确的有（）。2018真题",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","内容中必须包括事故发生后的避难和急救措施",true,{"key":16,"text":17,"correct":14},"B","项目部必须实行逐级交底制度，纵向延伸到班组全体人员",{"key":19,"text":20,"correct":14},"C","内容中必须包括针对危险点的预防措施",{"key":22,"text":23,"correct":24},"D","定期向交叉作业的施工班组进行口头交底",false,{"key":26,"text":27,"correct":14},"E","涉及“四新”项目的单项技术设计必须经过两阶段技术交底","ABCE","本题考查的是安全技术交底。选项D，交底必须是书面形式的。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]