[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141938":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141938,799,1,"单选题","施工安全控制程序包括：①安全技术措施计划的落实和实施；②编制建设工程项目安全技术措施计划；③安全技术措施计划的验证；④确定每项具体建设工程项目的安全目标；⑤持续改进。其正确顺序是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","②-③-④-①-⑤",false,{"key":16,"text":17,"correct":14},"B","②-④-①-③-⑤",{"key":19,"text":20,"correct":21},"C","④-②-①-③-⑤",true,{"key":23,"text":24,"correct":14},"D","④-②-③-①-⑤","本题主要考查施工安全控制程序。 施工安全控制程序包括：确定每项具体建设工程项目的安全目标；编制建设工程项目安全技术措施计划；安全技术措施计划的落实和实施；安全技术措施计划的验证；持续改进。 综上所述，本题正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]