[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141920":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141920,799,1,"单选题","在两类危险源中，第一类危险源控制的方法有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","增加设备安全系数，提高可靠性",false,{"key":16,"text":17,"correct":18},"B","消除危险源，限制危险物质",true,{"key":20,"text":21,"correct":14},"C","进行故障---安全设计",{"key":23,"text":24,"correct":14},"D","设置安全监控系统","本题主要考查风险控制的方法。 B项：第一类风险源控制的方法有两种，防止事故发生和避免或者减少事故损失。消除危险源、限制危险物质属于防止事故发生，所以B项正确。 ACD项：ACD项均属于第二类风险源的控制方法，而非第一类风险源的控制方法。所以ACD项错误。 综上所述，本题正确选项是B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]