[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141916":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141916,799,1,"单选题","对于建设工程项目施工中（ ）的风险，应考虑投资效果更佳的解决方案或不增加额外成本的改进措施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可容许",true,{"key":16,"text":17,"correct":18},"B","可忽略",false,{"key":20,"text":21,"correct":18},"C","重大",{"key":23,"text":24,"correct":18},"D","中度","本题主要考查风险控制措施。 基于不同风险水平的风险控制措施如下表： 对于建设工程项目施工中可容许的风险，只有风险已经降低，否则应考虑投资效果更佳的解决方案或不增加额外成本的改进措施。 综上所述，本题正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]