[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141876":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141876,799,1,"单选题","对于需要试生产的建设工程项目，建设单位应当在项目投入试生产之日起（ ）个月内向环保行政主管部门申请对其项目配套的环保设施进行竣工验收。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","2",{"key":19,"text":20,"correct":21},"C","3",true,{"key":23,"text":24,"correct":14},"D","4","本题考核的是职业健康安全与环境管理的主要任务。 对于需要试生产的建设工程项目，建设单位应当在项目投入试生产之日起3个月内向环保行政主管部门申请对其项目配套的环保设施进行竣工验收。 综上所述，正确选项为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]