[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141869":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141869,799,1,"单选题","对于应当拆除的工程，建设单位应当在拆除工程施工（ ）日前，将有关的拆除措施资料报送建设工程所在地的县级以上的地方人民政府主管部门或者其他有关部门备案。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","30",false,{"key":16,"text":17,"correct":18},"B","15",true,{"key":20,"text":21,"correct":14},"C","14",{"key":23,"text":24,"correct":14},"D","20","本题主要考查对拆除施工程序的了解。 依据《建设工程安全生产管理条例》，建设单位应在拆除工程施工前15日将有关资料报拆除工程所在地县级以上建设行政主管部门或者其他有关部门备案。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]