[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141868":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141868,799,1,"单选题","项目竣工后，（ ）应向审批建设工程项目环境影响报告书、环境影响报告或者环境影响登记表的环境保护行政主管部门申请，对环保设施进行竣工验收。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工单位",false,{"key":16,"text":17,"correct":14},"B","监理单位",{"key":19,"text":20,"correct":21},"C","建设单位",true,{"key":23,"text":24,"correct":14},"D","设计单位","本题主要考查建设工程职业健康安全与环境管理的要求。 项目竣工后，建设单位应向审批建设工程项目环境影响报告书、环境影响报告或者环境影响登记表的环境保护行政主管部门申请，对环保设施进行竣工验收。环保行政主管部门应在收到申请环保设施竣工验收之日起30日内完成验收。验收合格后，才能投入生产和使用。 综上所述，本题正确选项为C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]