[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141822":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141822,799,1,"单选题","在施工期间的质量监督中，对建设工程项目结构主要部位除了常规检查外，还要在分部工程验收时，要求建设单位将施工、设计、监理、建设方分别签字的质量验收证明在验收后（ ）天内报监督机构备案。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",true,{"key":16,"text":17,"correct":18},"B","7",false,{"key":20,"text":21,"correct":18},"C","14",{"key":23,"text":24,"correct":18},"D","21","本题主要考查施工期间的质量监督。 对建设工程项目结构主要部位（如桩基、基础、主体结构）除了常规检查外，还要在分部工程验收时，要求建设单位将施工、设计、监理、建设方分别签字的质量验收证明在验收后3天内报监督机构备案。 综上所述，本题正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]