[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141793":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141793,799,2,"多选题","在施工质量管理的工具和方法中，直方图一般用来（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","分析生产过程质量是否处于稳定状态",true,{"key":16,"text":17,"correct":14},"B","分析生产过程质量是否处于正常状态",{"key":19,"text":20,"correct":14},"C","分析质量水平是否保持在公差允许范围之内",{"key":22,"text":23,"correct":14},"D","整理统计数据，了解统计数据的分布特征",{"key":25,"text":26,"correct":27},"E","找出影响质量的主要因素",false,"ABCD","本题主要考查的是直方图法的应用。 直方图的主要用途有： （1）整理统计数据，了解分布特征； （2）观察分析生产过程质量是否处于正常、稳定和受控状态以及质量水平是否保持在公差允许范围内。 综上所述，正确选项为ABCD。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]