[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141754":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141754,799,2,"多选题","下列施工质量事故属于由技术原因引发的包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","结构设计计算错误",true,{"key":16,"text":17,"correct":14},"B","对水文地质情况判断错误",{"key":19,"text":20,"correct":21},"C","监理单位质量管理体系不完善",false,{"key":23,"text":24,"correct":21},"D","检测仪器设备失准",{"key":26,"text":27,"correct":21},"E","严重的自然灾害","AB","本题主要考察施工质量事故发生的原因 AB项：属于技术原因，故AB项正确。 CD项：属于管理原因，故CD项错误。 E项：属于人为事故和自然灾害原因，故E项错误。 综上所述，本题正确选项是AB项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]