[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141702":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141702,799,1,"单选题","建设单位应在工程竣工验收前（ ）个工作日前，将验收时间、地点、验收组名单书面通知该工程的工程质量监督机构。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",true,{"key":16,"text":17,"correct":18},"B","3",false,{"key":20,"text":21,"correct":18},"C","14",{"key":23,"text":24,"correct":18},"D","15","本题主要考查的是正式竣工验收的内容。 建设单位应在工程竣工验收前7个工作日前，将验收时间、地点、验收组名单书面通知该工程的工程质量监督机构。 综上所述，本题正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]