[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141699":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141699,799,1,"单选题","当建设工程按合同要求全部完成后，承包人向发包人提供了完整的竣工资料和竣工验收报告，发包人应在收到竣工验收报告后（ ）天内组织验收。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":21},"C","28",true,{"key":23,"text":24,"correct":14},"D","30","本题主要考查竣工验收。 发包人收到竣工验收报告后28天内组织验收，并在验收后14天内给予认可或提出修改意见。承包人应当按要求进行修改并承担因自身原因造成修改的费用。发包人收到承包人送交的竣工验收报告后28天内不组织验收或者在组织验收后14天内不提出修改意见则视为竣工验收报告已经被认可。 综上所述，本题正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]