[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141697":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141697,799,1,"单选题","单位工程完工后，（ ）应组织检查、评定，符合验收标准后，向建设单位提交验收申请。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工单位",true,{"key":16,"text":17,"correct":18},"B","设计单位",false,{"key":20,"text":21,"correct":18},"C","建设主管部门",{"key":23,"text":24,"correct":18},"D","质量监督机构","本题考核的是单位工程竣工验收组织的程序。 单位工程作为具有独立使用功能的完整的建筑产品，进行竣工质量验收。《建筑工程施工质量验收统一标准》（GB50300-2001）规定：单位工程完工后，施工单位应自行组织有关人员进行检查评定，并向建设单位提交工程验收报告。建设单位收到工程验收报告后，应由建设单位（项目）负责人组织施工（含分包单位）、设计、监理等单位（项目）负责人进行单位（子单位）工程验收。 综上所述，正确选项为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]