[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141692":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141692,799,1,"单选题","建设工程项目竣工验收应由（ ）组织。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监理单位",false,{"key":16,"text":17,"correct":14},"B","政府质量监督机构",{"key":19,"text":20,"correct":21},"C","建设单位",true,{"key":23,"text":24,"correct":14},"D","施工单位","本题考核的是建设工程项目竣工质量验收。 当初步验收检查结果符合竣工验收要求时，监理工程师应将施工单位的竣工申请报告报送建设单位，着手组织勘察、设计、施工、监理等单位和其他方面的专家组成竣工验收小组并制定验收方案。建设单位应在工程竣工验收前7个工作日将验收时间、地点、验收组名单通知该工程的工程质量监督机构。建设单位组织竣工验收会议。 综上所述，正确选项为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]