[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141679":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141679,799,1,"单选题","根据《建筑工程施工质量验收统一标准》（GB50300-2013），关于检验批质量验收合格的说法，正确的是（ ）。( 2015真题 )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可由监理员组织验收",false,{"key":16,"text":17,"correct":18},"B","应具有完整的施工操作依据，质量检查记录",true,{"key":20,"text":21,"correct":14},"C","主控项目不需全部检验合格",{"key":23,"text":24,"correct":14},"D","一般项目的检查具有否决权","本题考查的是施工过程的质量验收。检验批应由专业监理工程师组织施工单位项目专业质量检查员、专业工长等进行验收。检验批质量验收合格应符合下列规定：（1）主控项目的质量经抽样检验均应合格；（2）一般项目的质量经抽样检验合格；（3）具有完整的施工操作依据、质量检查记录。参见教材98。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]