[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141674":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141674,799,2,"多选题","下列施工质量验收环节中，应由专业监理工程师组织施工单位项目专业质量负责人等进行验收的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","分部工程",false,{"key":16,"text":17,"correct":18},"B","分项工程",true,{"key":20,"text":21,"correct":14},"C","单项工程",{"key":23,"text":24,"correct":18},"D","检验批",{"key":26,"text":27,"correct":14},"E","单位工程","BD","本题考核的是监理工程师组织验收的内容。 国家标准《建筑工程施工质量验收统一标准》（GB 50300-2001）规定：检验批应由监理工程师（建设单位项目技术负责人）组织施工单位项目专业质量（技术）负责人等进行验收；分项工程应由监理工程师（建设单位项目技术负责人）组织施工单位项目专业质量（技术）负责人进行验收； 分部工程应由总监理工程师（建设单位项目负责人）组织施工单位项目负责人和技术、质量负责人等进行验收。 综上所述，正确选项为BD。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]