[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141665":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141665,799,1,"单选题","分部工程应由（ ）组织施工单位项目负责人和技术、质量负责人等进行验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总监理工程师",true,{"key":16,"text":17,"correct":18},"B","监理工程师",false,{"key":20,"text":21,"correct":18},"C","项目经理",{"key":23,"text":24,"correct":18},"D","业主","本题主要考查分部工程项目验收。 分部工程是由总监理工程师组织施工单位项目负责人、技术负责人及勘察、设计单位项目负责人进行工程验收。建设单位项目负责人对总监理工程师及工程项目各参与方项目负责人的质量行为给予监督、检查、管理。 综上所述，本题正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]