[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141656":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141656,799,2,"多选题","某施工项目为实施成本管理收集了以下资料，其中可以作为编制施工成本计划依据的有（ ）。2014",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","施工预算",true,{"key":16,"text":17,"correct":14},"B","签订的工程合同",{"key":19,"text":20,"correct":14},"C","分包合同",{"key":22,"text":23,"correct":24},"D","施工图预算",false,{"key":26,"text":27,"correct":14},"E","资源市场价格","ABCE","（1）投标报价文件；（2）企业定额、施工预算；（3）施工组织设计或施工方案；（4）人工、材料、机械台班的市场价； （5）企业颁布的材料指导价、企业内部机械台班价格、劳动力内部挂牌价格；（6）周转设备内部租赁价格、摊销损耗标准；（7）已签订的工程合同、分包合同（或估价书）（8） 结构件外加工计划和合同；（9）有关财务成本核算制度和财务历史资料；（10）施工成本预测资料；（11） 拟采取的降低施工成本的措施；（12）其他相关资料。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]