[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141644":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141644,799,1,"单选题","从建设工程项目的施工组织设计到（ ）的施工计划，在实施之前都必须进行对下逐级交底，其目的是使管理者的计划和决策意图为实施人员所理解。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","检验批",false,{"key":16,"text":17,"correct":14},"B","分部工程",{"key":19,"text":20,"correct":21},"C","分部分项工程",true,{"key":23,"text":24,"correct":14},"D","单位工程","本题主要考查施工交底。 根据相关程序，为了使管理者的计划和决策意图为实施人员所理解，从建设工程项目的施工组织设计到分部分项工程的施工计划，在实施之前都必须进行对下逐级交底。 综上所述，本题正确选项为C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]