[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141633":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141633,799,1,"单选题","某建设工程项目由于分包单位购买的工程材料不合格，导致其中某分部工程质量不合格。在该事件中，施工质量控制的监控主体是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工总承包单位",false,{"key":16,"text":17,"correct":14},"B","材料供应单位",{"key":19,"text":20,"correct":14},"C","分包单位",{"key":22,"text":23,"correct":24},"D","建设单位",true,"本题主要考查施工作业质量控制。 建设单位、监理单位、设计单位及政府的工程质量监督部门，在施工阶段依据法律法规和工程施工合同，对施工单位的质量行为和质量状况实施监督控制。在该事件中，施工质量控制的监控主体是建设单位。 综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]