[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141620":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141620,799,1,"单选题","在施工准备阶段，绘制模板配板图属于（ ）的质量控制工作。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","计量控制准备",false,{"key":16,"text":17,"correct":14},"B","测量控制准备",{"key":19,"text":20,"correct":21},"C","施工技术准备",true,{"key":23,"text":24,"correct":14},"D","施工平面控制","本题考查的是施工准备工作的质量控制。 施工技术准备是指在正式开展施工作业活动前进行的技术准备工作。这类工作内容繁多，主要在室内进行，例如：熟悉施工图纸，组织设计交底和图纸审查；审核相关质量文件，绘制各种施工详图（如测量放线图、大样图及配筋、配板、配线图等）等。 C项：绘制模板配板图属于施工技术准备的质量控制工作，故当选。 ABD项：ABD均属于现场施工准备工作的质量控制，故不当选。 综上所述，本题正确选项为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]