[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141605":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141605,799,2,"多选题","下列各施工生产要素的质量控制手段中，属于对劳动主体质量控制的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合理布置施工总平面图",false,{"key":16,"text":17,"correct":18},"B","坚持特殊工种持证上岗制度",true,{"key":20,"text":21,"correct":14},"C","禁止使用明令淘汰的施工方法",{"key":23,"text":24,"correct":18},"D","坚持分包商资质考核制度",{"key":26,"text":27,"correct":18},"E","组织项目管理者培训学习","BDE","本题考核的是质量控制的内容。 劳动主体的质量包括工程各类参与人员的生产技能、文化素养、生理体能、心理行为等方面的个体素质及经过合理组织充分发挥其潜在能力的群体素质。施工企业必须坚持对所选派的项目领导者、管理者进行质量意识教育和组织管理能力训练； 坚持对分包商的资质考核和施工人员的资格考核； 坚持工种按规定持证上岗制度。 综上所述，正确选项为BDE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]