[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141590":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141590,799,2,"多选题","施工质量计划的基本内容包括（ ）。 2016",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","质量总目标及分解目标",true,{"key":16,"text":17,"correct":18},"B","工序质量偏差的纠正",false,{"key":20,"text":21,"correct":14},"C","质量管理组织机构和职责",{"key":23,"text":24,"correct":14},"D","施工质量控制点及跟踪控制的方式",{"key":26,"text":27,"correct":14},"E","质量记录的要求","ACDE","本题考查的是施工质量计划的内容与编制方法。施工质量计划的基本内容一般应包括：工程特点及施工条件（合同条件、法规条件和现场条件等）分析；质量总目标及其分解目标；质量管理组织机构和职责，人员及资源配置计划；确定施工工艺与操作方法的技术方案和施工组织方案；施工材料、设备等物资的质量管理及控制措施；施工质量检验、检测、试验工作的计划安排及其实施方法与检测标准；施工质量控制点及其跟踪控制的方式与要求；质量记录的要求。参见教材80～181。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]