[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141588":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141588,799,2,"多选题","施工质量控制点的事前质量预控工作主要包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","确定质量检查检验方式及抽样的数量与方法",true,{"key":16,"text":17,"correct":14},"B","明确检查结果的判断标准及质量记录与信息反馈要求",{"key":19,"text":20,"correct":14},"C","明确质量控制的目标与控制参数",{"key":22,"text":23,"correct":14},"D","编制作业指导书和质量控制措施",{"key":25,"text":26,"correct":27},"E","掌握施工操作要领",false,"ABCD","本题主要考查施工质量控制点。 施工质量控制点事前控制管理主要包括以下几个方面：（1）明确质量控制的目标与控制参数；（2）编制作业指导书和质量控制措施；（3）确定质量检查检验方式及抽样的数量与方法；（4）明确检查结果的判断标准及质量记录与信息反馈要求等。 综上所述，本题正确选项为ABCD项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]