[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141585":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141585,799,1,"单选题","施工质量控制点应选择技术要求高、对工程质量影响大或是发生质量问题时危害大或（ ）的对象进行设置。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","劳动强度大",false,{"key":16,"text":17,"correct":18},"B","施工难度大",true,{"key":20,"text":21,"correct":14},"C","施工技术先进",{"key":23,"text":24,"correct":14},"D","施工管理要求高","本题主要考查施工质量控制点的设置与管理。 施工质量控制点应选择那些技术要求高、施工难度大、对工程质量影响大或发生质量问题时危害大的对象进行设置。 综上所述，本题正确选项为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]