[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141581":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141581,799,1,"单选题","建设工程项目的施工质量计划编制完成后，应经（ ）批准确认后执行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","企业技术负责人审核并报请工程监理单位或建设单位",true,{"key":16,"text":17,"correct":18},"B","项目经理审核并报请工程监理单位或建设单位",false,{"key":20,"text":21,"correct":18},"C","工程监理单位审核并报请建设单位",{"key":23,"text":24,"correct":18},"D","工程监理单位审核并报请工程质量监督机构","本题主要考查施工质量计划的审批。 审批程序如下： 所以建设工程项目的施工质量计划编制完成后，应经企业技术负责人审核并报请工程监理单位或建设单位批准确认后执行。 综上所述，本题正确选项是A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]