[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141579":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141579,799,1,"单选题","施工承包企业按监理工程师依据合同和相关法规审批的施工质量计划组织施工，如导致工程质量问题，则责任由（ ）承担。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":14},"B","监理单位",{"key":19,"text":20,"correct":21},"C","施工承包企业",true,{"key":23,"text":24,"correct":14},"D","监理单位和施工承包企业共同","本题考核的是施工质量计划的编制与审批。 施工质量计划在审批过程中，对监理工程师审查所提出的建议、希望、要求等意见是否采纳以及采纳的程度，应由负责质量计划编制的施工单位自主决策。在满足合同和相关法规要求的情况下，确定质量计划的调整、修改和优化，并对相应知执行结果承担责任。 综上所述，正确选项为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]