[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141578":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141578,799,1,"单选题","建设工程项目的施工质量计划应经施工企业（ ）审核批准后，才能提交工程监理单位或建设单位。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":14},"B","法定代表人",{"key":19,"text":20,"correct":14},"C","项目经理部技术负责人",{"key":22,"text":23,"correct":24},"D","技术负责人",true,"本题考核的是施工质量计划的审批。 施工单位的项目施工质量计划或施工组织设计的编制与审批应根据企业质量管理程序性文件规定的权限和流程进行。通常是由项目经理部主持编制， 经技术负责人审批，报企业组织管理层批准，并报送项目监理机构核准确认。 综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]